| AOI |
Yearly calibration fail |
Sony |
calibrate done. |
ton |
closed |
| AOI |
TR7700Q SII-S Installation (Belton) |
Belton |
Request HQ to upgrade the software.
Wait for the Cognex dongle and install CVL7.2.
Follow-up.(Ship out in June 29, 2026) |
aek |
on going |
| AOI |
AI verify host demo |
Chicony |
6/5/2026 - Set up verify host pc and test run one machine. The AI verify host pc received data normally but the image is not showing. Already mailed to Taiwan wait to apply the solution
7/5/2026 - Apply the RS AI interface key to RS pc and change the module setting inside RS software from AI client to AI interface. the image is now display on the RSAI software. Only defect images can be displayed today, already sent an email to RD still waiting for solutions.
8/5/2026 - The path that RSAI pc read and the actual path is not the same, RD suggest to rename all RS pc to be different. If this solution does not work then have to modify the system file. Today have to connect both pre flow and post flow to the RSAI. Both Pre and Post reflow RS have been connected to the RSAI pc, the golden image can display normally and both golden and defect image can be save to the ai_image and ai_golden image folder.
11/5/2026 - Continue to collect the data from preflow and postflow AOI. Customer wants to set up AI at the other production line have to discuss futher(total 4 AOI machines 2 Preflow and 2 Postflow)
12/5/2026 - Monitor the data and check the AI report in SFC to compare the difference.
18/5/2026 - Get the AI report from SPC to make report for line 6. For line 5 have to gather more data. Send some of the training dataset to RD team to train model. AI accuracy for line 5 Pre and Post flow is at 76%. Wait for customer decision to turn on AI auto confirm.
25/5/2026 - Turn on AI auto confirm for all machine (AI accuracy around 76%-80%) wait to make report for both line
8/6/2026 - The AI defect rate is too high so have to send AI dataset for training.
11/6/2026 - Send training dataset to RD
15/6/2026 - RD team sent the update version of verify host software. Plan to go the install
19/6/2026 - Installed the upgraded version for the customer wait for result. If the AI defect looks good will make report and send to customer |
phone |
on going |
| AOI |
Lighting control board damage |
QMB |
6/5 Tried to switch lighting control board with another machine, result after changing normal lighting control board the camara light is normal.
6/8 contact Alice to request part for replace.
6/23 Waiting for part arrival |
nooknick |
on going |
| AOI |
SFC modify |
NA |
2/3 Bowen: discuss with customer
AOI team leader Carson
Wait for Flannery reply possible solution
2/26 Solution: DLOCR with output tool, already send mail to sales Grainger
5/4 Granger requesting part.
5/15: Thai local will setup and evaluate.
6/9 Waiting for customer inform the installation date
6/23 Schedule install 27-June at line K27 |
nooknick |
on going |
| AOI |
3D Image Error |
KUSAuto |
5/15 Send Bug report to Bowen.
5/29 Request customer do Self Calibration.
6/8 Customer test production.
6/15 Customer test continious production.
6/22 Customer test production --> No issue. |
ryu |
closed |